The wet well site was excavated and de-watered before setting the concrete well.
Once the well was set, the intake pipe was tied into the well.
Pre-formed concrete sections were stacked and sealed to get the proper depth for the well.
The area was backfilled and compacted around the well.
Installation of the mainline pipe on the golf course is ongoing. Today, we should be finished with number 18. Mainline still needs to be installed on numbers 6,12, and 10. Once the mainline is complete, we will begin hole by hole installation of laterals and heads. Our plan is to start on holes nearest the lake and work in from there.
Mainline is continuing up 18 toward the practice area.