Friday, December 20, 2013

Irrigation update

We pushed as hard as we could, but the weather has brought the irrigation installation to a halt.  We were able to complete the installation of laterals and heads on holes 13, 14, and most of 16.  This is further than expected, but not as far as we had hoped for.  This past week did allow for us to pour the pump house floor and set the pump station in place.  The construction of the building will begin in early January. 

 The last of the pumps being lowered into place